What is the first step in the five-step approach to risk management?

  1. Develop plans

  2. Conduct impact assessment

  3. Confirm scope and current state

  4. Implement readiness

The correct answer is: Confirm scope and current state

The first step in the five-step approach to risk management involves confirming the scope and current state. This foundational step is critical because it sets the stage for effective risk assessment and management planning. By clearly defining the scope of the project or initiative and understanding the current state of affairs, organizations can identify potential risks and challenges more accurately later on in the process. In this phase, stakeholders gather information about existing conditions, resources, and external factors that might influence risk. Without this initial clarity, any subsequent steps such as conducting impact assessments, developing plans, or implementing readiness may be misguided or based on incorrect assumptions, potentially weakening the overall risk management strategy. Therefore, establishing an accurate understanding of the current environment and parameters is fundamental for the success of the entire risk management process.